20 August 2014
DETAILS
Mitigation Action
• Procure additional propylene to fulfill polypropylene
capacity
• Successfully negotiate with customers on shortage
of gasoline and gas oil
• Re-commission of Deep Catalytic Cracking (DCC),
running at 60%-70%, since 29 June 2014
• Successfully arrange for imports of HTVGO,
resulting in DCC higher utilization
Anticipated shutdown period
• VGOHT unit is now expected to shut down for
about 10 months due to purchases of long-lead machinery.
Claim Amount
• Property damage (PD) USD 40 m : USD 35m
(Less deductible USD 5 m)
• Business Interruption (BI) : USD 56m
(Losses of 10 months, less deductible 2 months)
SOURCE : WWW.SET.OR.TH
WWW.CHEMWINFO.COM BY KHUN PHICHAI